The Contractor brought their paving crew on-site this morning to mark and prepare for the final paving. The first phase of paving will begin on Tuesday morning at the south end of 14th Avenue and continue north towards East Cliff Drive. The paving crew will then move to 15th Avenue and work their way south toward the 15th Avenue pump station. This work is expected to be complete by the end of the day Wednesday.
The second phase of paving will take place Thursday and Friday and include work in the intersection of East Cliff Drive and 15th Avenue. During this work, the Contractor will be redirecting one lane of traffic into the center lane at a time.
The third and final phase of paving will take place Tuesday and Wednesday of next week and will include work on Blackpoint Lane, 16th Avenue and Geoffroy Drive. We will update you with more information as it becomes available.
Additionally, the Contractor is continuing work on the 15th Avenue Pump Station control panel enclosure and replacing a water line at the end of 15th Avenue.
Thanks again for your continued cooperation in the final phases of the project!