The Contractor will be removing plates and placing temporary pavement on Blackpoint Lane this morning. Vehicle access to Blackpoint Lane will be limited this morning while the work is completed.
After the Blackpoint Lane work is completed, the Contractor will be closing 16th Avenue this afternoon while the new manholes are tied in. Access will be maintained for residents inside the construction zone. Thru traffic connecting to the south end of 16th Avenue is encouraged to take Geoffroy Drive to bypass the construction zone. The Contractor expects this work to be complete by the end of this week.
Following the 16th Avenue tie-in, the Contractor will be tying in to the new manhole Geoffroy Drive.
Thanks for your continued patience!
Wednesday, April 27, 2016
Friday, April 22, 2016
Construction Update for Monday 4/25
The Contractor has completed the installation of the new sewer on Blackpoint Lane. The road will reopen later this afternoon once cleanup is complete. The final paving will be completed in a few weeks when the paving crew mobilizes to pave all project areas.
On Monday, the Contractor will return to Geoffroy Drive to complete the new sewer tie-in so the existing 16th Avenue pump station can be abandoned. This work will likely take the majority of the week to complete.
Please contact the project phone line if you have any questions or concerns. Thank you!
On Monday, the Contractor will return to Geoffroy Drive to complete the new sewer tie-in so the existing 16th Avenue pump station can be abandoned. This work will likely take the majority of the week to complete.
Please contact the project phone line if you have any questions or concerns. Thank you!
Monday, April 18, 2016
Blackpoint Lane Gravity Sewer
The Contractor is returning to Blackpoint Lane to install the new gravity sewer line. Access will be maintained for emergency vehicles and pedestrians at all times. Residents are strongly encouraged to use the temporary parking area provided at the end of Blackpoint Lane at the East Cliff Shopping Center.
Residential vehicular access will be available upon request, however, there may be a 15-30 minute delay so that the trench can be made safe for vehicular access.
Residential vehicular access will be available upon request, however, there may be a 15-30 minute delay so that the trench can be made safe for vehicular access.
Please feel free to contact the project phone line if you have any questions or concerns.
Monday, April 11, 2016
Limited Twin Lakes Beach Access
The Contractor is nearing the beach at the end of 14th Avenue while installing the new gravity sewer line. During the next few days, there will be limited access to Twin Lakes Beach through the gate at the end of 14th Avenue. The Contractor is asking that pedestrians wishing to access the beach wait near the gate until a crew member signals that it is safe to pass the open trench.
Please be mindful of the Contractor's crew as the delays are expected to be short.
Once the Contractor finishes installing the new line on 14th Avenue, work on the Blackpoint Lane sewer line will resume. Work could begin on Blackpoint Lane as soon as Monday.
Please be mindful of the Contractor's crew as the delays are expected to be short.
Once the Contractor finishes installing the new line on 14th Avenue, work on the Blackpoint Lane sewer line will resume. Work could begin on Blackpoint Lane as soon as Monday.
Friday, April 8, 2016
Project Update
The Contractor will continue installing the new sewer on 14th Avenue through the beginning of next week. Once complete, they will move to Blackpoint Lane to complete the new sewer installation. Work on Blackpoint may begin as soon as Thursday, depending on progress on 14th Avenue. Advanced notice will be provided.
Restoration around the new 15th Avenue pump station will also continue next week.
Restoration around the new 15th Avenue pump station will also continue next week.