Thursday, June 23, 2016

Project Clean Up & Slurry Seal

For the remainder of this week and beginning of next week, the Contractor will be completing miscellaneous items of work and clean-up tasks to complete the project. Final road resurfacing is scheduled to take place on Wednesday, June 29th between the hours of 8am to 5pm.
Areas of Road Resurfacing

The slurry seal Contractor will be distributing notices to the areas affected by this work, as well as posting "no parking" signs ahead of the work. While the work is taking place, there will be no vehicle, bicycle, or pedestrian access on the roads until the new surface has cured. Cure times will vary based on weather conditions, but may take as long as four hours to complete once placed.

Monday, June 20, 2016

Final Sewer Cleaning and Inspection

The Contractor will be performing final cleaning and inspection of the new sewer lines today. The crew will be performing work in all project areas so please drive carefully and follow the flaggers' instructions.

Thursday, June 2, 2016

East Cliff Drive Paving

The Contractor will be finishing the final section of new pavement in the westbound lane of the East Cliff Drive and 15th Avenue intersection today. The crew currently has the westbound and center lane closed with flaggers stationed at either end of the work area. Expect some short delays while heavy equipment moves around the work area. Please be cautious and follow the flaggers instructions.

Tuesday, May 31, 2016

Paving on Blackpoint Lane

The Contractor is beginning paving operations on Blackpoint Lane this morning. The new pavement is expected to be complete by the end of the day today. During the work, Blackpoint Lane will be closed to vehicle traffic. Residents are encouraged to park vehicles in the reserved parking area in the East Cliff Village parking lot and walk past the work zone.

Additionally, the Contractor will begin removing the existing pavement on 16th Avenue this morning.  Vehicle traffic is encouraged to use Geoffroy Drive to bypass the construction on 16th Avenue. The Contractor is expecting to place new pavement on 16th Avenue as soon as this afternoon.

Work is also continuing at the south end of 14th Avenue on the new grinder pump stations.

Wednesday, May 25, 2016

Paving Schedule Update

The Contractor has completed trench paving on 14th Avenue, and today will be starting paving on 15th Avenue. There will be no paving work for the remainder of the week. Paving work will resume on Tuesday, May 31st at Blackpoint Lane after the Memorial Day Holiday.

The Contractor will also continue lateral work at the end of 14th Avenue through the end of the week, and will continue abandonment and clean-up operations over the next couple of weeks throughout the project site.

Monday, May 23, 2016

Final Paving Beginning Soon

The Contractor brought their paving crew on-site this morning to mark and prepare for the final paving. The first phase of paving will begin on Tuesday morning at the south end of 14th Avenue and continue north towards East Cliff Drive. The paving crew will then move to 15th Avenue and work their way south toward the 15th Avenue pump station. This work is expected to be complete by the end of the day Wednesday.

The second phase of paving will take place Thursday and Friday and include work in the intersection of East Cliff Drive and 15th Avenue. During this work, the Contractor will be redirecting one lane of traffic into the center lane at a time.

The third and final phase of paving will take place Tuesday and Wednesday of next week and will include work on Blackpoint Lane, 16th Avenue and Geoffroy Drive. We will update you with more information as it becomes available.

Additionally, the Contractor is continuing work on the 15th Avenue Pump Station control panel enclosure and replacing a water line at the end of 15th Avenue.

Thanks again for your continued cooperation in the final phases of the project!

Monday, May 16, 2016

Work at 15th Avenue and East Cliff Drive

The Contractor will be installing a new drop connection in the manhole at the 15th Avenue and East Cliff Drive intersection today. Expect a small crew working in the intersection.

Traffic in the west bound lane is being temporarily redirected into the center lane around the work area. Please proceed through the area with caution.

Friday, May 13, 2016

Upcoming Work at 15th Avenue and East Cliff Drive Intersection

Today, the Contractor will begin demolition of the 16th Avenue pump station. You will notice a small crew and some heavy equipment on the side of Geoffroy Drive during the demolition.

Next week, the Contractor will be working in the intersection of 15th Avenue and East Cliff Drive to install a drop connection for the new force main. During the work, the Contractor will have traffic control signs and cones set up. Please pay attention to the Contractor's instructions and be alert when driving near the construction.

The final section of concrete at the 15th Avenue pump station driveway was poured last Tuesday. The driveway will be reopened next Monday.

Have a great weekend!

Friday, May 6, 2016

Geoffroy Drive Update

Due to unforeseen issues, the Contractor actually began the manhole tie-ins on Geoffroy Drive yesterday with work continuing in to next week. Geoffroy Drive will be closed during the course of the work. Thru traffic will be able to access the south side of Geoffroy Drive via 16th Avenue.

The 15th Avenue pump station driveway restoration remains on schedule with work expected to be complete by the end of next week.

Thanks for your continued cooperation!

Tuesday, May 3, 2016

Geoffroy Drive and 15th Avenue Pump Station Driveway Work

The Contractor will begin the manhole tie-ins on Geoffroy Drive tomorrow morning and is expecting the work to be completed by the end of next week. Geoffroy Drive will be closed during the course of the work. Thru traffic will be able to access the south side of Geoffroy Drive via 16th Avenue.

The 15th Avenue pump station site restoration is progressing nicely with the new driveway currently being installed. The driveway is expected to be complete by the end of next week as well.

As always, feel free to call the project information line with any comments or questions.

Wednesday, April 27, 2016

April 27th Project Update

The Contractor will be removing plates and placing temporary pavement on Blackpoint Lane this morning. Vehicle access to Blackpoint Lane will be limited this morning while the work is completed.

After the Blackpoint Lane work is completed, the Contractor will be closing 16th Avenue this afternoon while the new manholes are tied in. Access will be maintained for residents inside the construction zone. Thru traffic connecting to the south end of 16th Avenue is encouraged to take Geoffroy Drive to bypass the construction zone. The Contractor expects this work to be complete by the end of this week.

Following the 16th Avenue tie-in, the Contractor will be tying in to the new manhole Geoffroy Drive.

Thanks for your continued patience!

Friday, April 22, 2016

Construction Update for Monday 4/25

The Contractor has completed the installation of the new sewer on Blackpoint Lane. The road will reopen later this afternoon once cleanup is complete. The final paving will be completed in a few weeks when the paving crew mobilizes to pave all project areas.

On Monday, the Contractor will return to Geoffroy Drive to complete the new sewer tie-in so the existing 16th Avenue pump station can be abandoned. This work will likely take the majority of the week to complete.

Please contact the project phone line if you have any questions or concerns. Thank you!

Monday, April 18, 2016

Blackpoint Lane Gravity Sewer

The Contractor is returning to Blackpoint Lane to install the new gravity sewer line. Access will be maintained for emergency vehicles and pedestrians at all times. Residents are strongly encouraged to use the temporary parking area provided at the end of Blackpoint Lane at the East Cliff Shopping Center.



Residential vehicular access will be available upon request, however, there may be a 15-30 minute delay so that the trench can be made safe for vehicular access.

Please feel free to contact the project phone line if you have any questions or concerns.

Monday, April 11, 2016

Limited Twin Lakes Beach Access

The Contractor is nearing the beach at the end of 14th Avenue while installing the new gravity sewer line. During the next few days, there will be limited access to Twin Lakes Beach through the gate at the end of 14th Avenue. The Contractor is asking that pedestrians wishing to access the beach wait near the gate until a crew member signals that it is safe to pass the open trench.


Please be mindful of the Contractor's crew as the delays are expected to be short.

Once the Contractor finishes installing the new line on 14th Avenue, work on the Blackpoint Lane sewer line will resume. Work could begin on Blackpoint Lane as soon as Monday.

Friday, April 8, 2016

Project Update

The Contractor will continue installing the new sewer on 14th Avenue through the beginning of next week. Once complete, they will move to Blackpoint Lane to complete the new sewer installation. Work on Blackpoint may begin as soon as Thursday, depending on progress on 14th Avenue. Advanced notice will be provided.

Restoration around the new 15th Avenue pump station will also continue next week.

Tuesday, March 29, 2016

14th Avenue Open Cut

This week the Contractor is continuing to install the new gravity sewer on 14th Avenue. This work is anticipated to continue through the end of this week and into next week.

Once 14th Avenue is complete, the Contractor will then return to the installation of the new gravity sewer on Blackpoint Lane. This work is tentatively scheduled for week of April 11, 2016.

Wednesday, March 23, 2016

Returning to 14th Avenue

The Contractor is expecting to finish work on 16th Avenue this afternoon. Beginning tomorrow, the Contractor will resume excavation on 14th Avenue for the new gravity line. The gravity line installation is expected to take at least a week depending on unforeseen conditions. Updates will be posted here as the schedule becomes more concrete.



During installation of the gravity line on 14th Avenue, the Contractor will be closing the west lane around the work area to vehicle traffic. The Contractor will be directing traffic through the shared east lane.

Thanks for your continued patience. Feel free to call the project information line with any questions or concerns at (831) 708-8285.

Tuesday, March 22, 2016

Backfilling on 16th Avenue

The Contractor is continuing to pull the shoring and backfill the pit on 16th Avenue today. They expect the pit to be completely backfilled by the end of the day tomorrow, but could finish as early as this afternoon. Additionally, the manhole on Geoffroy Drive will be tested today. Once the test has been passed, the Contractor can begin backfilling the manhole.

The Contractor plans to return to 14th Avenue this Thursday to continue excavating for the new gravity line. This gravity line is expected to take a couple of weeks to install. A more concrete schedule can be made once the work gets underway.

Thursday, March 17, 2016

Schedule Update

After running into some unforeseen sight conditions, the Contractor has postponed work on the new gravity sewer line on 14th Avenue. The Contractor will finish installing the manholes on 16th Avenue and Geoffroy Drive for the rest of this week and into the beginning of next week.

Beginning on Monday, the Contractor will be removing the shoring for the pit on 16th Avenue. During this phase of work, 16th Avenue will be closed for 3-24 hour days. Access will be maintained for all residents and the south side of 16th Avenue can be accessed by using Geoffroy Drive.

The Contractor will return to work on the 14th Avenue gravity line on Thursday of next week at the earliest. Once the gravity line is complete, work on Blackpoint Lane will resume.

Thanks for your continued cooperation and patience!

Monday, March 14, 2016

14th Avenue Gravity Sewer Installation

The Contractor started excavating on 14th Avenue for the new gravity sewer line this morning. The new gravity line is expected to be installed by the end of next week. During installation, the Contractor will be closing the west lane around the work area to vehicle traffic. The Contractor will be directing traffic through the shared east lane.



The Contractor will also be installing the new manholes on 16th Avenue. The street will continue to be closed during the work. Residents are encouraged to use Geoffroy Drive to access the south end of 16th Avenue.

Thanks for your continued patience. Feel free to call the project information line with any questions or concerns at (831) 708-8285.