Monday, March 14, 2016

14th Avenue Gravity Sewer Installation

The Contractor started excavating on 14th Avenue for the new gravity sewer line this morning. The new gravity line is expected to be installed by the end of next week. During installation, the Contractor will be closing the west lane around the work area to vehicle traffic. The Contractor will be directing traffic through the shared east lane.



The Contractor will also be installing the new manholes on 16th Avenue. The street will continue to be closed during the work. Residents are encouraged to use Geoffroy Drive to access the south end of 16th Avenue.

Thanks for your continued patience. Feel free to call the project information line with any questions or concerns at (831) 708-8285.