Due to the weather conditions, the Contractor is unable to proceed with the open cut sewer work on Blackpoint Lane. They are however still able to perform manhole work on Blackpoint Lane, as well as various other locations on the project. Expect localized closures at the manhole locations through the end of the week.
The Contractor is also continuing work on the new generator pad at the 15th Avenue Pump Station.
The Contractor will resume open cut operations on Blackpoint Lane when weather conditions allow. Potentially the end of next week or the week of March 21st.