New 15th Avenue Pump Station |
The Contractor is also beginning preparatory work to begin installing the pits for the trenchless sewer installation. They are currently working on installing a temporary sewer bypass on Geoffroy Drive. The excavation of the pits is tentatively scheduled to begin the week of January 11, 2016, though this schedule is not yet confirmed. A more specific timeframe will be provided as soon as it is available.
Friday there will be no work due to the New Year's Day holiday.