Tuesday, December 29, 2015

New Year's Holiday Week Update

The Contractor continues to work in two areas. Progress continues at the new 15th Avenue Pump Station which is beginning to take shape. It is scheduled to be tested and put into operation in early January.
New 15th Avenue Pump Station



The Contractor is also beginning preparatory work to begin installing the pits for the trenchless sewer installation. They are currently working on installing a temporary sewer bypass on Geoffroy Drive. The excavation of the pits is tentatively scheduled to begin the week of January 11, 2016, though this schedule is not yet confirmed. A more specific timeframe will be provided as soon as it is available.

Friday there will be no work due to the New Year's Day holiday.