Wednesday, December 16, 2015

Sewer Bypass Update

The Contractor is finishing up the 16th Avenue sewer bypass and starting the bypass on 14th Avenue today. The crew will be cleaning up 16th Avenue before moving their equipment over to 14th Avenue.

Expect a small crew and some equipment on 14th Avenue in the area shown on the map in the previous post. There may be some short traffic delays, but access to all residences will be maintained.

Additionally, work on the 15th Avenue pump station control panel slab continues. The Contractor expects the slab to be poured this Friday.