Project Clean Up & Slurry Seal

For the remainder of this week and beginning of next week, the Contractor will be completing miscellaneous items of work and clean-up tasks to complete the project. Final road resurfacing is scheduled to take place on Wednesday, June 29th between the hours of 8am to 5pm.
Areas of Road Resurfacing

The slurry seal Contractor will be distributing notices to the areas affected by this work, as well as posting "no parking" signs ahead of the work. While the work is taking place, there will be no vehicle, bicycle, or pedestrian access on the roads until the new surface has cured. Cure times will vary based on weather conditions, but may take as long as four hours to complete once placed.

Monday, June 20, 2016

Final Sewer Cleaning and Inspection

The Contractor will be performing final cleaning and inspection of the new sewer lines today. The crew will be performing work in all project areas so please drive carefully and follow the flaggers' instructions.

Thursday, June 2, 2016

East Cliff Drive Paving

The Contractor will be finishing the final section of new pavement in the westbound lane of the East Cliff Drive and 15th Avenue intersection today. The crew currently has the westbound and center lane closed with flaggers stationed at either end of the work area. Expect some short delays while heavy equipment moves around the work area. Please be cautious and follow the flaggers instructions.