Wednesday, January 27, 2016

Blackpoint Lane and 14th Avenue

The Contractor completed drilling on Blackpoint Lane today. They will return tomorrow between 10am and 2pm to finish the preparation of the receiving pit.

In the meantime, the drillers will move to 14th Avenue to begin drilling the receiving pit. Again working hours are 7:30am to 5:00pm with heavy equipment operation between 8:30am and 4:30pm.



Additionally, PG&E is scheduled to be on site tomorrow to bring in power to the new 15th Avenue pump station.