Friday, April 22, 2016

Construction Update for Monday 4/25

The Contractor has completed the installation of the new sewer on Blackpoint Lane. The road will reopen later this afternoon once cleanup is complete. The final paving will be completed in a few weeks when the paving crew mobilizes to pave all project areas.

On Monday, the Contractor will return to Geoffroy Drive to complete the new sewer tie-in so the existing 16th Avenue pump station can be abandoned. This work will likely take the majority of the week to complete.

Please contact the project phone line if you have any questions or concerns. Thank you!